Sunday, October 23, 2016

The home stretch

We are down to the last week! Toe molding was added mid-week. The floors are now finished and look amazing, particularly the bedrooms.   









Window screens are nearly finished. and the brackets to hang them have been added to the exterior.


The kitchen and bathroom sinks are FINALLY back from the re-finisher and ready to be installed.



The toilet has been purchased and is ready for installation. The verbiage on the box cracks me up.


The door hinges and window hardware have been cleaned and painted.  Doors to be hung this week.



The ceiling fans have been installed in all the rooms and on the front porch.




The chandeliers in the kitchen are now installed as well.


I just ordered the last light fixtures (God bless Amazon Prime!). Time to schedule the furniture delivery and then on to decorating and move-in.

That's all from Wisteria Bend for now.

~Christy